CONSTRUCTION EQUIPMENT MANAGEMENT NOTES 10

NOTES - 10
EQUIPMENT MANAGEMENT TIPS FOR THE CONSTRUCTION ENGINEERS 
AND PLANT & MACHINERY ENGINEERS
AN INTRODUCTION TO CONSTRUCTION PLANT AND EQUIPMENT
HOW TO KEEP RECORDS OF EQUIPMENT PLANT AND MACHINERY FOR OPTIMUM UTILIZATION

I. Purpose of Records :
It is important that records should be kept not only to allow the compilation of progress reports, but also as a means of checking performance against work program so as to improve output where necessary or to recognize or reallocate resources when specific items are lagging behind program. Records of actual performance, when linked with statements of site conditions and factors such as breakdown, skill of operators etc. form available guide to the planning and estimating of further projects.
Three types of records should be kept :
i. Progress records
ii. Work output records of individual machines and team of machines
iii. Equipment records.
II. Progress Records
Records of progress may be kept in a variety of forms, but the method adopted should be as simple as possible, and to be of real value, must allow for immediate comparison with planned programme and show at a glance, the actual break-up made, often on percentage basis.
Suitable methods are:
i. Work programme as progress records
ii. Bar graph progress chart
iii. Line graphs
iv. Pictorial records.
III. Work output records ‚ - Records of actual output of individual machines and if desired, of team of machines, will not only be useful on the projects itself to help in analysing any causes of delay in progress of work but will prove of great value for further planning and estimating.
To enable these records to be compiled, plant supervisor's reports will be necessary.
IV. Plant Supervisor's Reports:
Each plant supervisor should be required to complete shift report at the end of each shift showing relevant information about the machines which have been under his control during the shift. The report should not be confused with plant operators daily log which is mainly concerned with servicing and fuel consumption.
Typical items to be entered on plant supervisors report for each machine are :
i. Task on which employed.
ii. Total work carried out e.g. number of trips performed, total mileage or number of vehicles loaded, depending on type of task.
iii. Number of minutes worked per hour.
iv. Servicing periods.
v. Remarks on delay and waiting times with reasons.
V. Basic record of equipment to be maintained in Department:
Complete record of equipment should be maintained in two documents viz;
i. Log Book
ii. Daily/Monthly working data
iii. History Book
VI. Log Book
The Log Book is to be utilised for two purposes:
i. for a technical control to evaluate how the machine is performing, and
ii. for getting the 'plant hours' performance classified by works.
To determine performance, the total plant hours put in by a machine must be known and causes of 'trouble' should be classified. The log book records the 'consumption of fuels and lubricants, since the performance of the machine can be judged readily from these figures. It records the work on which the machine was employed indicating the officer on whose requisition the machines was utilised.
The log book should be given as much importance for proper maintenance as for measurement book.
VII. Daily/Monthly working data
Log book also gives record of utilisation of machinery. Other data such as sickness, idleness etc. are not readily available in log book. The data is equally important to indicate performance of machine.
For this purpose the data is to be maintained in the form of daily working machinery. Monthly abstract should be prepared in four copies.
VIII. History Books
It is possible with records in history book to evaluate the general condition of a machine at any time, to decide the nature and extent of the next overhaul, to help in scaling the spare parts required in future and to assess it is value.
IX. Maintenance Register
The Maintenance Register for the following should be maintained :
i. Daily maintenance
ii. Weekly maintenance
iii. 100 to 175 hours maintenance
iv. 250 hours maintenance
v. 500 hours maintenance
vi. 1000 hours maintenance
vii. 2000 hours maintenance
X. Supervision
The importance of adequate and efficient supervision at all levels of project involving the use of engineer construction plant cannot be too strongly emphasized. However carefully a project is planned, result will be unsatisfactory unless supervision is efficient throughout the work.
Lack of supervision always results in misuse of machine and wastage of machine time.
The purpose of supervision is not only to see that work is carried out correctly to specifications laid down and the machines are properly used and output maintained at consistently high level but also to foresee difficulties and likely bottlenecks which may reduce output and to take steps to obstacle them before they occur.
It is then supervisor's responsibility to :
i. Ensure that all concerned under his command are clear on their task.
ii. See that machines are used to best advantage and operators take their task correctly
iii. Ensure that the work is properly done to the specification laid down.
iv. Take early steps to deal with difficulties in order to assist the operators to maintain their output where difficulties develop which he cannot deal with satisfactorily from his own resources; report them without delay to next supervisor, with the recommendation as to how they can best be overcome.
v. Always be thinking ahead to foresee likely difficulties and bottlenecks to the progress of work before they occur so that steps can be taken in time to prevent them or failing this to reduce this adverse effect on out-put.
vi. Ensure that mechanical servicing of machines is carried out thoroughly at correct times and that any sign of mechanical trouble are reported so that steps can be taken to remedy them and prevent breakdown and delays occurring during work.
vii. See application of safety precautions is observed.
viii. During work and particularly before end of day working period, see that precautions are taken as regards drainage or to prevent work already done, before being damaged or machine immobilized by sudden changes in weather and other causes.
ix. Keep record of process during the work and output of the machine in local conditions under which they are working. Such records will be of great value for planning work on the same machine for future operation.

Table - 1
EQUIPMENT RECORD -SAMPLE
...........................Project

Project Serial No............... Equipment ..............
Manufacturer ....................Model, Type etc.........
Manufacturer's Sl.No......... .Other Nos...............
Purchase order ................. Measurement book........
Description..................... cost billed.............
............... Cost billed.............
............... Transport ..............
............... Erection & trail........

Total
Received from ..............................................
Date of Receipts ............... ........................
Engine Make......................Model & Sl.No............
Aux. Engine Make ............... Model & Sl. No..........
B.H.P of Engine ............... .........
Tyre Sizes ................... .........
Aux. Equipment...................Make & Model & capacity......
EL System........................
Hyd. System.....................
Air System.......................
Clutch...........................Transmission.................
PCU..............................
Table - 2
HISTORY BOOK -SAMPLE
First Sheet
No. of machine
Short description
Previous History Book No.
Name of Organisation
To whom issued

PART - I
Manufacturer's Data
1. No. of Machine
2. Name of Machine
3. Capacity
4. Model and Serial No.
5. Make, Model and HP of Engine
6. Serial No. of Engine
7. Manufacturers of Sub assemblies
a. EI system
b. Transmission and clutch
c. Air Compressor of Hydraulic System
8. Tyre sizes and recommended pressures
9. Capacities of :
1. Crank Chambers
2. Transmission
3. Final drive
4. Hydraulic
5. Coolant
6. Other information
10. Ref. to spare parts catalogue and services book No.
Purchase Data
1. Reference to purchase order
2. Supplied by or received in transfer from
3. Date of receipt at
4. Date first put to use
5. Condition when received
6. Price paid to supplier
7. Cost of transport erection and trail

Rs.________________
Total cost Rs. ________________
Table - 4
FORMS FOR MACHINERY RECORD - SAMPLE

The various forms required for technical control and accounts are compiled here. They should be printed in suitably bound books. Where more than on copy is required, it is a good plan to have a distinguishing colour specified for each.
1. Daily Operation Report
2. Eight Hours Maintenance Report
3. Daily Field Repair Report
4. Daily Servicing Report
5. Accident/ Breakdown Report
6. Shift Charge Report
7. Weekly Plant Details and Progress Report
8. Monthly Report of Material used on Machines

9. Advice of Transfer Debit between charges.

No comments:

Post a Comment